Chiller Replacement in Central London…

Last week, Mechanical Movements successfully completed a chiller replacement, for a prestigious client in Central London. Using a mobile tower crane, the replacement began by removing four redundant chillers, steel work, and adjacent pipework. The team then installed new steel work, which was fabricated by Mechanical Movements specifically for the chillers, and then proceeded to […]

Lift & Install Operation in Coventry…

Mechanical Movements were in Coventry last week installing several bits and pieces at Oakley Grove School, Leamington Spa… The items installed included: 3x Air Source Heat Pumps at 3550kg/ 3.5tonne 1x Sitewide Heating Pump at 2000kg/2tonne 1x Electric Transformer at 5000kg / 5tonne Sundry Pipework at 2000kg/2.5tonne 3x pallets of solar panel equipment at 2500kg/2.5tonne […]

Easter Bank Holiday Steel Work Supply & Installation…

Mechanical Movements team were in London this easter weekend completing the supply and installation of steel work for Megan Renewables Installations at Acton Town Hall & Leisure Centre After the necessary structural surveys and designs were completed, the Mechanical Movements team began fabricating and galvanising the steelwork in-house. The steelwork was then installed to support […]