‘Ten Green Bottles Hanging on the Wall’

This week, we’re admiring a recent job we completed at a large prominent data centre in Dagenham, for our client – Pheonix.

These 10 magnificent bright green cooling tower vessels, each weighing 1,700kg each, were laying down flat at ground level and required lifting and securing into their steel frames.

Using 2 x 50-tonne mobile tower cranes, we safely lifted each tank into its position within the frame, then bolting them securely to keep them fixed in place. We also had one of our MEWPs on-site (Mobile Elevating Work Platform), which we utilised to remove the lifting tackle from each unit once they were secure.

The entire project was completed in 3 days and resulted in a very impressive wall of green bottles!