Having recently completed works at the Ocado offices in Hertfordshire, Mechanical Movements visited the Birmingham facilities last week to complete another important project.
Our expert team were responsible for the replacement of 4no condensers and 4no downflow units, situated within various levels of the building.
Following the safe delivery of the equipment to site, our movement specialists used a Hiab lorry to carefully lift 2no condensers 22m high, into the roof level enclosure. The same reliable equipment was then used to successfully replace 4no downflow units within the level 3 comms room.