• Churchill Place, Canary Wharf

    Date: Aug 2026

    Location: 

    Canary Wharf, London

    Overview:

    Following secure storage at our Gravesend facility, the AHUs have been transported to site & are being carefully manoeuvred up to the 34th floor.

    Utilising our telehandlers for unloading & porta gantries to safely build & position the units within the building.

  • Energy Centre, Lasdun Wall

    Date: July 2026

    Location: 

    University of East Anglia

    Overview:

    We’re proud to have completed the storage, delivery & installation of two air-cooled chillers for our client at a major energy centre project.

    Our team managed the full logistics package, from secure storage at our Gravesend facility, through carefully planned transport & delivery, to the safe lifting & final positioning of the units on their Big Foot support systems.

  • Central London

    Date: July 2026

    Location: 

    London

    Overview:

    Working within a busy city-centre environment required careful planning, expert coordination and precise execution. Using our specialist lifting and plant movement equipment, we safely transported each unit to site before manoeuvring and installing them into their designated locations, ensuring the programme remained on schedule.

  • Longleat Safari Park, Wiltshire

    Date: July 2026

    Location: 

    Wiltshire

    Overview:

    Our team were on site at Longleat Safari Park, delivering & installing a new pump station as part of an infrastructure upgrade within the park.

    From carefully transporting the unit to site, through to offloading, positioning & final installation, the project required detailed planning, specialist equipment & close coordination with the Longleat team to ensure the works were completed safely & efficiently.

  • Medical Facility, Surrey

    Date: July 2026

    Location: 

    Surrey

    Overview:

    Our team recently delivered the installation of multiple Air Handling Units (AHUs) & large packaged plant rooms at the a new medical facility in Surrey last week.

    Using a Liebherr TM 1300-6.2 with a 38.5m luffer we safely lifted & positioned each unit at a significant working radius, with every lift carefully planned and executed to ensure the project was completed efficiently & safely.

  • London

    Date: June 2026

    Location: 

    London

    Overview:

    Another milestone reached this weekend for our Lifting Team as we successfully installed the final of 10 riser modules on this major project in Central London, marking the closing stages of the riser installation package.

  • Data Centre, London

    Date: May 2026

    Location: 

    London

    Overview:

    Our team has successfully installed a large cooling fan wall system as part of an ongoing London data centre project.

    Careful planning, specialist lifting equipment, and experienced installation crews ensured the units were positioned safely and efficiently, keeping the project on track.

  • Bishopsgate, London

    Date: April 2026

    Location: 

    Bishopsgate, London

    Overview:

    This chiller was delivered to our Gravesend depot, mechanically dismantled, transported to site, then reassembled and installed by our movement team.

  • Royal Mail, Heathrow

    Date: April 2026

    Location: 

    Heathrow, London

    Overview:

    Our team carried out the removal, fabrication, and installation of various structural steel solutions across the site, ensuring every stage was delivered safely, efficiently, and to the highest standard.

  • Croydon

    Date: April 2026

    Location: 

    Croydon

    Overview:

    Our team successfully delivered the full scope of works for the replacement of BAC water towers—managing not only the complex lift itself, but also the transport of wide loads to and from site in a busy city-centre environment.

  • Greenwich Peninsula Low Carbon Energy Centre

    Date: March 2026

    Location: 

    Greenwich, London

    Overview:

    We successfully completed the installation of heavy boilers along with a wide range of heavy plant and equipment to support this landmark sustainable infrastructure project.

    This development is designed to deliver significant environmental benefits.

     

  • Sadlers Wells

    Date: March 2026

    Location: 

    London

    Overview:

    We were on site to carry out a compressor changeover on the chiller system. The team managed the removal of the existing unit & installation of the replacement within the FläktGroup setup, ensuring everything was correctly positioned and ready to maintain system performance.

  • Financial District, London

    Date: March 2026

    Location: 

    London

    Overview:

    Our team carried out the delivery and installation of a number of plant skids into the sub-basement at Level -4. Each skid was stored and prepared at our depot before being carefully transported into central London and installed on site.

  • Leighton Leisure and Community Centre

    Date: March 2026

    Location: 

    Clipstone Brook, Bedford

    Overview:

    Our team at Mechanical Movements Ltd were busy on site assembling and installing a range of mechanical plant, including the build of FläktGroup flat‑pack Air Handling Units (AHUs) and associated plant equipment that supported the building’s ventilation and environmental control systems.

  • Westminster, London

    Date: Feb 2026

    Location: 

    Westminster, London

    Overview:

    Our team planned the install, coordinated the rooftop works, and delivered a smooth handover.

  • Westbury Hotel

    Date: Dec 2025

    Location: 

    Westbury Hotel, London

    Overview:

    The operation required precise planning and meticulous execution, as the equipment was carefully hoisted onto the roof, positioned within the plant tower, and then lowered into the basement areas.

  • Data Centre, Slough

    Date: Dec 2025

    Location: 

    Data Centre, Slough

    Overview:

    All 20 brand-new chillers turned up at our depot. We tucked them away in our secure storage for over a year.
    Our 55-ton Leibherr got a proper workout unloading them all initially, then loading them back up one by one as the client’s schedule called for each replacement. Then it was off to site with the team, all the lifting kit, traffic management gear, and everything else needed to get the job done right.

  • Oxford Street, London

    Date: Dec 2025

    Location: 

    Oxford Street, London

    Overview:

    Full road closure on Oxford Street with Mechanical Movements managing all traffic control.
    Spierings AT5 crane deployed — 30° jib, 34m boom, 23m radius lifts.  Carrier AquaSnap frames lifted through tight access and repositioned with tandem rigs.  Unit assembled piece by piece. Bulk tipper handled old plant removal via roof‑level lifting skip.

  • Barbican Centre, London

    Date: Oct 2025

    Location: 

    Disney Plus’s ‘Alien: Earth’ European Red Carpet Premiere at the Barbican Centre

    Overview:

    Transport and precise positioning of diverse alien-themed art installation pieces throughout the venue
    Our skilled team expertly manoeuvred various installation elements around the site and up to elevated levels, including the movement of the infamous Xenomorph eggs and containment units.

  • Lothbury

    Date: Aug 2025

    Location: 

    Lothbury, London

    Overview:

    After more than 12 months of planning, the crane lift for the Roof Plant has been completed, with the AHU and two extract fans now safely installed. This complex lift was carefully executed with the support of Mechanical Movements.

  • Harley Street

    Date: Aug 2025

    Location: 

    Harley Street,London

    Overview:

    Our team successfully completed a complex cranage operation on Harley Street utilizing a Spierings AT6. This project involved multiple air source heat pumps and a challenging chiller installation in one of London’s most demanding urban environments.

  • Arthur Street

    Date: May 2025

    Location:

    London, Arthur Street

    Overview:

    The removal of the existing chiller system from roof level, and the successful delivery and cranage of brand new replacement chiller and plant work.

  • Harley Street

    Date: June 2025

    Location:

    London, Harley Street

    Overview:

    Cranage operations including the relocation of existing Air Source Heat Pumps, delivery of new ASHP’s and Chiller plant using a Spierings AT6 with 52meter boom length.

     

     

     

  • Triton Square

    Date: Apr 2025

    Location:

    London

    Overview:

    The completion of a series of complex lifts using a 650-tonne LTM1650 crane equipped with 180 tonnes of counterweights and a 72m luffing jib.

  • The Cursitor Building, London

    Date: Apr 2025

    Location:

    Chancery Lane, Holborn

    Overview:

    The installation of three new chillers, each weighing 1,500kg, along with two condensers, each weighing 380kg, on a five-floor office building.

  • London Metropolitan University

    Date: Apr 2025

    Location:

    Aldgate, London

    Overview:

    The installation of a new 6-tonne chiller, while simultaneously utilising our Hiab to install additional condensers onto a lower roof.

  • Croydon, London

    Date: Mar 2025

    Location:

    South London

    Overview:

    The removal of several large dry air coolers, each weighing around 650kg, using two of our Hiab lorries in unison.

  • Canary Wharf, London

    Date: Mar 2025

    Location:

    East London

    Overview:

    The project involved removing 12 redundant water towers and replacing them with 9 new, highly efficient units, ensuring the safe handling of over 300 tonnes of materials.

  • Westfield, London

    Date: Feb 2025

    Location:

    West London

    Overview:

    Successful installation of 3 air handling units (AHUs), 6 condensers and A wide range of ductwork.

  • Thames Court, London

    Date: Feb 2025

    Location:

    Central London

    Overview:

    Successful completion of phase 3 chiller changeover, with the use of the impressive 6300l-1 crane from our skilled team.

  • Nine Elms, London

    Date: Jan 2025

    Location:

    South West London

    Overview:

    The replacement of a 4.5-tonne water tower was expertly carried out by our team using our 100-tonne cranes, operating at a 20-metre radius.

  • Central London

    Date: Jan 2025

    Location:

    Central London

    Overview:

    The installation of a new Daikin chiller, expertly carried out by our lifting team.

  • Upper Thames Street, London

    Date: Dec 2024

    Location:

    London

    Overview:

    The installation of AHU components, the heaviest weighing 1 tonne, was carried out using a small reach truck for precise manoeuvring with specialised equipment.

  • Knightsbridge, London

    Date: Dec 2024

    Location:

    London

    Overview:

    The relocation of several trees, each weighing one tonne, was carried out by hoisting them to a 45-meter radius using an AT4 mobile tower crane.

  • Upper Thames Street, London

    Date: Nov 2024

    Location:

    London

    Overview:

    The removal of a 7-tonne chiller and its replacement with a new, state-of-the-art unit, using an AT7 mobile tower crane.

  • Data Centre, Slough

    Date: Nov 2024

    Location:

    Slough

    Overview:

    The removal of two 16-tonne chillers and replacement with two new 13-tonne chillers

  • Great Windmill St, London

    Date: Oct 2024

    Location:

    London

    Overview:

    The removal of 14 aging condensers and the installation of 14 new units, each weighing approximately 300kg.

  • Skanska, Victoria Street

    Date: Sep 2024

    Location:

    London

    Overview:

    An installation of several large mechanical components, including 4-tonne buffer vessels, 3-tonne pump skids, and expansive air handling units (AHUs), in the lower basement of a building within the new redevelopment project on the southern end of Victoria Street.

  • Dolphin House, Grosvenor Road

    Date: Sep 2024

    Location:

    London

    Overview:

    The relocation of a transformer at Dolphin House.

  • The Capital Hotel, London

    Date: Sep 2024

    Location:

    Knightsbridge

    Overview:

    The installation of three new high-efficiency condensers.

  • Student Accommodation, London

    Date: Sep 2024

    Location:

    Billingsgate, Canary Wharf

    Overview:

    An installation of 6-tonne transformers, 5-tonne generators, 8-tonne plate heat exchangers, 3-tonne booster pump sets, 4-tonne sprinkler pump sets, and several control panels.

  • Temple Circus House, Bristol

    Date: Aug 2024

    Location:

     Bristol

    Overview:

    The removal of old Air Handling Units (AHUs) and chillers, in preparation for a new installation.

  • Bank Street, London

    Date: Aug 2024

    Location:

    Canary Wharf

    Overview:

    The removal of 2x 16-tonne chillers and an installation of 2x 25-tonne chillers.

  • Guinness Microbrewery, London

    Date: July 2024

    Location:

    Langley Street, Covent Garden

    Overview:

    Lift and installation of 2 air source heat pumps (ASHP), 1 chiller, 2 buffer vessels, and a booster set.

  • Charing Cross Rd, London

    Date: June 2024

    Location:

    Charing Cross Road, London

    Overview:

    Lift and installation of 1x Generator, 1x Package Plant Room, 4 x Air Handling Units (AHU), 2 x Electrical Panels, and 5 x Condensers.

  • Charing Cross Rd, London

    Date: May 2024

    Location:

    Charing Cross Raod, London

    Overview:

     Installation of 30 condensers and air source heat pumps (ASHP) on the plant deck mezzanine on the roof of the building.

  • Mandrake Spa & Hotel, London

    Date: May 2024

    Location:

    West London

    Overview:

    Crane lift of plant air conditioning units, air handling units (AHUs), pump sets, and packaged plant rooms onto 2 separate plant areas across 2 different roofs of the building.

     

  • Central London

    Date: Apr 2024

    Location:

    Central London

    Overview:

    Removal of 4 redundant chillers, steel work and adjacent pipework. Installation of 2 new 6-tonne chillers along with new steelwork and pipework.

     

  • Oakley Grove School, Coventry

    Date: Apr 2024

    Location:

    Leamington Spa, Coventry

    Overview:

    Installation of 3x Air Source Heat Pumps, 1x Sitewide Heating Pump,1x Electric Transformer, Sundry Pipework, 3x pallets of solar panel equipment, and 4x control panels.

  • Phoenix, Peterborough

    Date: Apr 2024

    Location:

    Peterborough

    Overview:

    50 x 1500kg Internal AHUs, 25 x 4500kg External AHUs, and Internal Switch Gear 2000kg installation.

  • Barnet County Court, Finchley

    Date: Mar 2024

    Location:

    Finchley, Barnet

    Overview:

     2x Mitsubishi Air Source Heat Pumps (ASHP), switch gear and a 1.3 tonne chiller installation.

  • Ergro Group, London

    Date: Feb 2024

    Location:

    Thomas More Square, London

    Overview:

    Delivery and installation of 2x 9.5 tonne chillers.

  • Phoenix, London

    Date: Feb 2024

    Location:

    Coleman St, London

    Overview:

    Delivery and installation of 2x 5-tonne transformers.

  • Dalkia, London

    Date: Jan 2024

    Location:

    Stratford & Islington, London

    Overview:

     Storage, Delivery and installation of loading bay extraction systems at Queen Elizabeth Olympic Park and Sadler’s Wells Theatre.

  • Powis Place, London

    Date: Jan 2024

    Location:

    Bloomsbury, London

    Overview:

    Removal of 2 redundant chillers from the roof, and the replacement of 3 brand new 2.2 tonne chillers using a mobile tower crane.

  • Phoenix, Peterborough

    Date: Jan 2024

    Location:

    Peterborough

    Overview:

     Installation and lift of several external Air Handling Units (AHUs), Internal AHUs and large amounts of switch gear and control panels.

  • Nutwood House, Canterbury

    Date: Oct 2023

    Location:

    Canterbury

    Overview:

    Delivery and Installation of 2x 1.6-tonne chillers using our HIAB lorry positioning the units onto Anti-vibration Mounts (AVM).

  • Dolphin House, London

    Date: Oct 2023

    Location:

    Pimlico, London

    Overview:

    Installation and lowering of a 5-tonne transformer onto a platform in a basement switch room, accessed via a space-restricted lightwell.

  • He Simm Group, Wembley

     

    Client: HE Simm Group

    Date: Sept 2023

    Location:

    Wembley, London

    Overview:

    Transport and installation of several riser pipes and service modules, across 6 x buildings varying in size from 9 to 20 floors

  • Bupa Hospital, Luton

     

    Date: Sept 2023

    Location:

    Luton, London

    Overview:

    Movement and installation of critical plant components, including 2 x 40ft chillers each weighing 9 tonnes, as well as 2 x AHUs each weighing 7 tonnes

  • Power Base, Harley street

     

    Client: Power Base

    Date: August 2023

    Location:

    Harley Street, London

    Overview:

    Transport and installation of a compact 2-tonne chiller and a 950kg ASHP using a Terex Demag AC35L 35-tonne crane.

  • Brighton Hospital, Sussex

    Date: August 2023

    Location:

    Brighton, Sussex

    Overview:

    Using a colossal 300-tonne crane, Mechanical Movements Completed the first of a three-phase operation to replace all chillers at Brighton Hospital, Sussex.

  • Optimise, Canary Wharf

    Client: Optimise Group

    Date: July 2023

    Location:

    Canary Wharf, London

    Overview:

    Removal of all critical building services plant from the roof level of the 23 storey tower at One Cabot Square.

  • Wates Group, Bristol

    Client: Wates Group

    Date: July 2023

    Location:

    Avon Street, Bristol

    Overview:

    Transport and installation of 8 electrical switchgear panels, to a new 5 storey commercial office building for Contractor Wates Group.

  • Ergro Group, Kensington

    Client: Ergro Group

    Date: June 2023

    Location:

    Kensington, London

    Overview:

    Storing and transportation of four new condenser units, using a mobile tower crane and load spreading mats to remove the 28 redundant condensers and place the new ones. Once installed, all condenser debris and equipment were cleared from the site.

  • Maidstone Hospital, Kent

    Date: June 2023

    Location:

    Maidstone, Kent

    Overview:

    Movement and installation of an Air Handling Unit (AHU), using our HIAB lorry to deliver the unit in 7 sections, with the heaviest weighing in at 2300 kg.

  • Boiler Change, Stevenage

    Date: May 2023

    Location:

     Stevenage, Hertfordshire

    Overview:

    Removed the 15-tonne existing boiler from the site before preparing the plant area with load-bearing road plates, pull points, turfers, and hoists, ready for the new and more efficient 12-tonne boiler to be manoeuvred in.

  • Buntingford School,  East Hertfordshire

    Client: Buntingford School

    Date: March 2023

    Location:

     East Hertfordshire

    Overview:

    Installation of Air Handling Units (AHUs) with contactor Morgan Sindall, using our lifting equipment to manoeuvre them into the first floor, and dismantling them alongside the manufacturer’s guidance.

  • Discovery Park, Sandwich

    Client: Discovery Park Commercial Estate

    Date: March 2023

    Location:

    Sandwich, Kent

    Overview:

    Mechanical Movements positioned and assembled four Air Handling Units (AHUs), which were flat-packed and divided into 1500kg sections, using an external goods hoist and gantry to gain access to the roof plant room.

  • White Hart Street, High Wycombe

    Date: March 2023

    Location:

    White Hart Street, High Wycombe

    Overview:

    Lift and install of 2 condensers and flatpack Flackwood Air handling Units delivered using our 26-tonne rigged HIAB lorry.

     

  • Beaumont Hotel, Mayfair

    Client: Vulcan

    Date: February 2023

    Location:

    Mayfair, London

    Overview:

    Lowering of Air Handling Units (AHUs), water heaters, cylinders, pump sets, booster sets and water treatment systems, through a large access opening, into lower basement.

  • Saffron House, Holborn

    Client: Sale

    Date: February 2023

    Location:

    Saffron House, Hatton Garden, Holborn

    Overview:

    Removal of redundant chillers and steel work from the roof level plant room, before using a mobile 100ton crane to lift and install 5no 2500kg chillers, and 2no condensers into the plant enclosure.

  • British Museum Archaeological Research Centre

    Client: LJJ Ltd

    Date: January 2023

    Location:

    British Museum Archaeological Research Centre, Reading

    Overview:

    Using our all terrain telehandler, our movement specialists installed 10no AHUs. Each unit consisted of 5no sections which were double stacked and bolted together once positioned correctly. Our team were also responsible for fitting a number of pumps and vessels within an external plant room.

  • Mercedes Benz Oxford

    Client: T Clark

    Date: January 2023

    Location: Oxford

    Overview:

    Mechanical Movements were appointed to complete the movement and installation of several small AHUs within the Mercedes Benz showroom in Oxford.

  • Sadler’s Wells East Theatre

    Client: Retail/Leisure Client

    Date: January 2023

    Location: Stratford, London

    Overview:

    Mechanical Movements were required to install a variety of plant around the venue, including 2no 6000kg chillers, 3no AHUs, pumps, extract fans and control panels. Anti-vibration mounts and pads were used to prevent disruptive vibrations travelling down into the theatre.

  • White Hall Place

    Client: IAC Innovation

    Date: November 2022

    Location:  White Hall Place, Westminster

    Overview:

    Our operatives fabricated and installed 3no large steel frames to situate all plant onto before lifting a wide variety of plant including, 2no chillers, 2no dry air coolers, 7no AHUs, 6no condensers, 24 pallets of slab, 50no sections of duct work and 100no pieces of pipework. All equipment was lifted using an AT6 mobile tower crane and road closures were implemented throughout works.

  • Google UK Headquarters

    Client: BAC

    Date: November 2022

    Location:  Google UK Headquarters, Kings Cross

    Overview:

    Use of our sturdy artic lorry, 2 x 22tonne rigged lorries and a smaller 7.5tonne lorry to deliver 6 x 15tonne water cooling towers to Google Headquarters. Prior to transportation, each tower was dismantled into 5 manageable sections, facilitating the transportation process.

  • ‘Here’ Building

    Client: Commercial Landlord

    Date: November 2022

    Location:  Thames Valley Park, Reading

    Overview:

    Installing 2no AHUs into a brand-new basement gym. Pallet trucks were used to carefully move the equipment into a small plant room located on the gym floor.

  • Ocado Offices

    Client: Ocado Group

    Date: October 2022

    Location:  Hatfield, Hertfordshire

    Overview:

    Removing and replacing cooling systems within the Ocado offices using a LTM1060 crane. We carefully removed 8no 350kg dry air-cooling condensers from the roof plant room, replacing these with 2 newer units. 6no downflow units, each weighing 450kg were also replaced within the live server rooms.

  • BBC Television Centre

    Client: Commercial Consultant

    Date: October 2022

    Location:  White City, West London

    Overview:

    Use of a 22-ton rigged Hiab lorry to replace a 1500kg plate heat exchanger within a basement plant room.

  • KOKO Camden

    Client: Make One

    Date: October 2022

    Location:  Camden, London

    Overview:

    Use of a 22-ton rigged Hiab lorry to lift a 600kg door, fitting it back onto the side of the KOKO building, a renowned music venue in Camden.

  • 17 Clerkenwell Close

    Client: Parkeray

    Date: October 2022

    Location:  Clerkenwell, London

    Overview:

    Utilising a mobile Bocker crane to lift 2no condensers, 14m high onto the roof level of the commercial property. Each 370kg condenser was carefully lifted at an 18m radius, before being placed onto Big Foot support systems.

  • Porters House

    Client: Innovation Air Conditioning and Building Services

    Date: October 2022

    Location:  Islington, London

    Overview:

    Using an AT6 mobile tower crane to lift 1no AHU into the rear lower ground plant room. The AHU was split into 3 manageable sections, with the heaviest section weighing 2170kg. Following the completion of the ground-level works, 4no condensers were lifted into the roof plant room and manoeuvred into their final positions.

  • Midas House

    Client: Working Environments

    Date: September 2022

    Location: Woking, Surrey

    Overview:

    Following the careful storage and delivery of the plant, a Hiab lorry was used to lift all units onto site. The new plant included 1no 3.5 tonne heat pump, 2no 900kg buffer vessels, 3no 500-800kg plate heat exchangers and 2no side stream filters, and a telehandler was utilised to shift all equipment into its final position.

  • Swan House

    Client: Ergro

    Date: September 2022

    Location: Holborn, London

    Overview:

    Using a Terex Challenger 3180, we completed a chiller replacement job, removing 2no chillers from the roof of the property. Once all redundant plant had been removed, we were required to lift 4no condensers and 2no MVHRs into the building, carefully manoeuvring them into their final positions.

  • One Nine Elms

    Client: Designer Group

    Date: August 2022

    Location: Nine Elms, London

    Overview:

    Storing, delivering and installing 4no cooling towers, 2no control panels and 2no pressurisation units to a new 56-storey mixed-use tower development.

  • City University London

    Client: Ergro

    Date: August 2022

    Location: Clerkenwell, London

    Overview:

    Completion of a lifting project using a AT7 Spierings crane to remove a substantial 13tonne AHU, replacing it with a newer, more efficient unit.

  • St Anthony’s House

    Client: Easy Cool Solutions

    Date: July 2022

    Location: Oxford Square, Newbury

    Overview:

    Completion of a lifting project using a Spierings AT6 crane to successfully lift a 215kg condenser up onto the roof of an office development.

  • Ark Acton Academy

    Client: Local Authority

    Date: July 2022

    Location: Acton, London

    Overview:

    Installation of 4 plate heat exchangers and 3 new boilers at the new Ark Acton Academy site.

  • Great Ormond Street Hospital

    Client: Great Ormond Street Hospital

    Date: July 2022

    Location: Central London

    Overview:

    Use of a 46-ton Challenger 3180 crane to complete a chiller replacement project. A stair climber was then used to remove a 600kg plate heat exchanger from a basement plant room.

  • AbbVie House

    Client: Commercial Consultant

    Date: June 2022

    Location: Maidenhead, Berkshire

    Overview:

    Use of a Demag AC-160 at a 22m radius to successfully lift each 4750kg chiller component into its final position.

  • Sadler’s Wells East Building

    Client: Retail/Leisure Client

    Date: June 2022

    Location: Stratford, London

    Overview:

    Using a Terex 2500 Telehandler, the Mechanical Movements team safely unloaded a plant skid off of a lorry before operating a hoist to manoeuvre each component up into the mezzanine plant room.

  • Astrazeneca Campus

    Client: Commercial Consultant

    Date: June 2022

    Location: The Discovery Centre, Cambridge

    Overview:

    Complex lifting project using a tower crane to lift 1 x condenser and 3 x carrier chillers into the building, before manoeuvring each unit into its final position within the plant room.

  • Brooke Hall Student Accommodation

    Client: The University of the Arts London

    Date: May 2022

    Location: Camberwell, London

    Overview:

    Completion of a boiler changeover. Using a rigged Hiab lorry we removed 2 redundant boilers and associated components, before delivering and installing 2 new boilers.

  • Abbey Place

    Client: Box & Charnock

    Date: May 2022

    Location: Abbey Wood, London

    Overview:

    Complex lifting project using a Terex Demag AC35 crane to lift 1no generator and 1no CHP into a plant enclosure.

  • Stoke Park Golf Club & Hotel

    Client: Retail/Leisure Client

    Date: May 2022

    Location: Buckinghamshire

    Overview:

    We were required to excavate trenches using a 2.5 tonne machine before installing new heating services and systems throughout the 300-acre estate.

  • Habib Bank

    Client: Commercial Consultant

    Date: April 2022

    Location: Moorgate, London

    Overview:

    Use of a 100ton crane to complete a contract lift. We were responsible for the storage, delivery and full installation of some substantial commercial HVAC plant.

  • Swiss Cottage Library

    Client: Ergro

    Date: March 2022

    Location: Camden, London

    Overview:

    Plant removal project using a Spierings AT-4 crane at a 44m radius. Redundant equipment was removed from multiple plant areas, including 2no chillers, 3no air handling units, 6no condensers and 2no extract fans.

  • Bank Street

    Client: Commercial Office Client

    Date: December 2021

    Location: Canary Wharf, London

    Overview:

    Installing new downflow cooling systems into the European Bank for Reconstruction & Development (EBRD) building.

  • 4 Handyside Street

    Client: Commercial Consultant

    Date: November 2021

    Location: Kings Cross, London

    Overview:

    Complex lifting project using a crane lift to transport large structural steelwork, along with 2 Dry Air Coolers up onto the roof of a 11 storey tower.

  • Greenwich Mechanical Plant

    Client: Alcatel Submarine Networks

    Date: November 2021

    Location: Greenwich

    Overview:

    Use of a 100ton mobile crane to lift replacement machinery onto a newly fabricated mezzanine level, following a strip out of a redundant mechanical plant.

  • KOKO Camden

    Client: Retail/Leisure Client

    Date: October 2021

    Location: Camden, London

    Overview:

    Use of a 26tonne Bocker truck-mounted crane to lift 3no. panes of glass from a lorry bed at ground level, to the roof of the KOKO building.

  • New Gate Street

    Client: Commercial Landlord

    Date: October 2021

    Location: London

    Overview:

    Using a 300tonne crane with a 60m luffing jib, the Mechanical Movements team safely managed the placement of chillers and Air Handling Units onto the roof of an office building in New Gate Street.

  • Underground Carpark Candleford

    Client: Commercial Consultant

    Date: September 2021

    Location: Candleford, Northamptonshire

    Overview:

    Replacement of ventilation equipment in an underground carpark using a Telehandler 2506 fitted with a scrubber to remove damaged ventilation fans.  These were replaced with new 2no. fans which were lifted using block and tackle.

  • Crawley Civic Offices

    Client: Public Authority

    Date: September 2021

    Location: Crawley

    Overview:

    Coordinating the placement of equipment for the heating and ventilation systems of new civic offices in Crawley.  This consisted of multiple lifts of new equipment using an onsite tower crane.

  • Gravesend Canal Basin

    Client: Private Client

    Date: September 2021

    Location: Gravesend, Kent

    Overview:

    Manoeuvre of a 20ft sailing yacht within the canal basin in Gravesend, using a 55tonne Liebherr mobile crane.

  • Canary Wharf

    Client: Commercial Consultant

    Date: June 2021

    Location: London

    Overview:

    Use of specialist lifting equipment to complete a coil replacement in the water tower of an iconic bank building.

  • AkzoNobel Offices

    Client: AkzoNobel

    Date: June 2021

    Location: Slough, Berkshire

    Overview:

    Lifting project using a 60 tonne mobile crane to lift and manoeuvre 4no. Air Handling Units into a steel frame.

  • Vale Royal

    Client: Commercial Landlord

    Date: May 2021

    Location: Islington, London

    Overview:

    Contract lift of a new generator onto the roof of a 34m high commercial building, using a Spierings AT6 mobile tower crane.

  • Norwich Crown Court

    Client:

    Date: May 2021

    Location: Norwich

    Overview:

    Replacement of cooling towers on the roof of Norwich Crown Court, using a 100tonne mobile crane.

  • Featherstone Street

    Client: Commercial Developer

    Date: February 2021

    Location: Shorditch

    Overview:

    Various contract lifts to position commercial heating and air conditioning equipment into the basement of a 12 storey, mixed-use, new build construction site.

  • Westminster Air Conditioning

    Client: Commercial Landlord

    Date: January 2021

    Location: Westminster

    Overview:

    Use of on-site tower cranes to lift 3 Air Conditioning units onto the rooftop of a 15storey mixed-use retail and residential building.

  • Student Accommodation Block, London

    Client: Prominent London University

    Date: October 2020

    Location: Vauxhall, London

    Overview:

    Storage and delivery of 4 no pump vessel and boiler skids to a Student Accommodation block.  Following this, an on-site tower crane was used to hoist the boiler skid packages up to a counter lever deck.

  • St Peter’s Hospital

    Client: St Peter’s Hospital

    Date: October 2020

    Location: Chertsey

    Overview:

    Use of a LT1045 mobile crane to lift two Trane chillers onto the roof of a two-storey hospital building.

  • Commercial Office Tower Hamlets

    Client: Commercial Office Client

    Date: July 2020

    Location: Tower Hamlets, London

    Overview:

    Use of a 300ton crane to lift a 6ton generator onto the 10th floor of a 10-storey office building.  The unit was then assembled before being manoeuvred into its final position within the plant room.

  • Lincoln’s Inn Lift

    Client: Royal College of Surgeons

    Date: June 2020

    Location: Lincoln’s Inn, Central London

    Overview:

    Use of an on-site tower crane to lift 4 sections of package plantroom onto the roof of a 6-storey learning facility.

  • White City

    Client: Prominent London University

    Date: April 2020

    Location: White City, London

    Overview:

    Movement of 8 giant potted trees using flatbed Hiab lorries. This was necessary to make room for the erection of a scaffold hoist which was required for a nearby construction project.

  • Dagenham Data Centre

    Client: Pheonix

    Date: April 2020

    Location: Dagenham

    Overview:

    Lifting project in Dagenham featuring 10 cooling tower vessels which needed bolting into their steel frames.