Data Centre, Slough
Date: Nov 2024
Location:
Slough
Overview:
Removal of two 16-tonne chillers and replacement with two new 13-tonne chillers
Date: Nov 2024
Location:
Slough
Overview:
Removal of two 16-tonne chillers and replacement with two new 13-tonne chillers
Date: Oct 2024
Location:
London
Overview:
The removal of 14 aging condensers and the installation of 14 new units, each weighing approximately 300kg.
Date: Sep 2024
Location:
London
Overview:
An installation of several large mechanical components, including 4-tonne buffer vessels, 3-tonne pump skids, and expansive air handling units (AHUs), in the lower basement of a building within the new redevelopment project on the southern end of Victoria Street.
Date: Sep 2024
Location:
London
Overview:
The relocation of a transformer at Dolphin House.
Date: Sep 2024
Location:
Knightsbridge
Overview:
The installation of three new high-efficiency condensers.
Date: Sep 2024
Location:
Billingsgate, Canary Wharf
Overview:
An installation of 6-tonne transformers, 5-tonne generators, 8-tonne plate heat exchangers, 3-tonne booster pump sets, 4-tonne sprinkler pump sets, and several control panels.
Date: Aug 2024
Location:
Bristol
Overview:
The removal of old Air Handling Units (AHUs) and chillers, in preparation for a new installation.
Date: Aug 2024
Location:
Canary Wharf
Overview:
The removal of 2x 16-tonne chillers and an installation of 2x 25-tonne chillers.
Date: July 2024
Location:
Langley Street, Covent Garden
Overview:
Lift and installation of 2 air source heat pumps (ASHP), 1 chiller, 2 buffer vessels, and a booster set.
Date: June 2024
Location:
Charing Cross Road, London
Overview:
Lift and installation of 1x Generator, 1x Package Plant Room, 4 x Air Handling Units (AHU), 2 x Electrical Panels, and 5 x Condensers.
Date: May 2024
Location:
Charing Cross Raod, London
Overview:
Installation of 30 condensers and air source heat pumps (ASHP) on the plant deck mezzanine on the roof of the building.
Date: May 2024
Location:
West London
Overview:
Crane lift of plant air conditioning units, air handling units (AHUs), pump sets, and packaged plant rooms onto 2 separate plant areas across 2 different roofs of the building.
Date: Apr 2024
Location:
Central London
Overview:
Removal of 4 redundant chillers, steel work and adjacent pipework. Installation of 2 new 6-tonne chillers along with new steelwork and pipework.
Date: Apr 2024
Location:
Leamington Spa, Coventry
Overview:
Installation of 3x Air Source Heat Pumps, 1x Sitewide Heating Pump,1x Electric Transformer, Sundry Pipework, 3x pallets of solar panel equipment, and 4x control panels.
Date: Apr 2024
Location:
Peterborough
Overview:
50 x 1500kg Internal AHUs, 25 x 4500kg External AHUs, and Internal Switch Gear 2000kg installation.
Date: Mar 2024
Location:
Finchley, Barnet
Overview:
2x Mitsubishi Air Source Heat Pumps (ASHP), switch gear and a 1.3 tonne chiller installation.
Date: Feb 2024
Location:
Thomas More Square, London
Overview:
Delivery and installation of 2x 9.5 tonne chillers.
Date: Feb 2024
Location:
Coleman St, London
Overview:
Delivery and installation of 2x 5-tonne transformers.
Date: Jan 2024
Location:
Stratford & Islington, London
Overview:
Storage, Delivery and installation of loading bay extraction systems at Queen Elizabeth Olympic Park and Sadler’s Wells Theatre.
Date: Jan 2024
Location:
Bloomsbury, London
Overview:
Removal of 2 redundant chillers from the roof, and the replacement of 3 brand new 2.2 tonne chillers using a mobile tower crane.
Date: Jan 2024
Location:
Peterborough
Overview:
Installation and lift of several external Air Handling Units (AHUs), Internal AHUs and large amounts of switch gear and control panels.
Date: Oct 2023
Location:
Canterbury
Overview:
Delivery and Installation of 2x 1.6-tonne chillers using our HIAB lorry positioning the units onto Anti-vibration Mounts (AVM).
Date: Oct 2023
Location:
Pimlico, London
Overview:
Installation and lowering of a 5-tonne transformer onto a platform in a basement switch room, accessed via a space-restricted lightwell.
Client: HE Simm Group
Date: Sept 2023
Location:
Wembley, London
Overview:
Transport and installation of several riser pipes and service modules, across 6 x buildings varying in size from 9 to 20 floors
Date: Sept 2023
Location:
Luton, London
Overview:
Movement and installation of critical plant components, including 2 x 40ft chillers each weighing 9 tonnes, as well as 2 x AHUs each weighing 7 tonnes
Client: Power Base
Date: August 2023
Location:
Harley Street, London
Overview:
Transport and installation of a compact 2-tonne chiller and a 950kg ASHP using a Terex Demag AC35L 35-tonne crane.
Date: August 2023
Location:
Brighton, Sussex
Overview:
Using a colossal 300-tonne crane, Mechanical Movements Completed the first of a three-phase operation to replace all chillers at Brighton Hospital, Sussex.
Client: Optimise Group
Date: July 2023
Location:
Canary Wharf, London
Overview:
Removal of all critical building services plant from the roof level of the 23 storey tower at One Cabot Square.
Client: Wates Group
Date: July 2023
Location:
Avon Street, Bristol
Overview:
Transport and installation of 8 electrical switchgear panels, to a new 5 storey commercial office building for Contractor Wates Group.
Client: Ergro Group
Date: June 2023
Location:
Kensington, London
Overview:
Storing and transportation of four new condenser units, using a mobile tower crane and load spreading mats to remove the 28 redundant condensers and place the new ones. Once installed, all condenser debris and equipment were cleared from the site.
Date: June 2023
Location:
Maidstone, Kent
Overview:
Movement and installation of an Air Handling Unit (AHU), using our HIAB lorry to deliver the unit in 7 sections, with the heaviest weighing in at 2300 kg.
Date: May 2023
Location:
Stevenage, Hertfordshire
Overview:
Removed the 15-tonne existing boiler from the site before preparing the plant area with load-bearing road plates, pull points, turfers, and hoists, ready for the new and more efficient 12-tonne boiler to be manoeuvred in.
Client: Buntingford School
Date: March 2023
Location:
East Hertfordshire
Overview:
Installation of Air Handling Units (AHUs) with contactor Morgan Sindall, using our lifting equipment to manoeuvre them into the first floor, and dismantling them alongside the manufacturer’s guidance.
Client: Discovery Park Commercial Estate
Date: March 2023
Location:
Sandwich, Kent
Overview:
Mechanical Movements positioned and assembled four Air Handling Units (AHUs), which were flat-packed and divided into 1500kg sections, using an external goods hoist and gantry to gain access to the roof plant room.
Date: March 2023
Location:
White Hart Street, High Wycombe
Overview:
Lift and install of 2 condensers and flatpack Flackwood Air handling Units delivered using our 26-tonne rigged HIAB lorry.
Client: Vulcan
Date: February 2023
Location:
Mayfair, London
Overview:
Lowering of Air Handling Units (AHUs), water heaters, cylinders, pump sets, booster sets and water treatment systems, through a large access opening, into lower basement.
Client: Sale
Date: February 2023
Location:
Saffron House, Hatton Garden, Holborn
Overview:
Removal of redundant chillers and steel work from the roof level plant room, before using a mobile 100ton crane to lift and install 5no 2500kg chillers, and 2no condensers into the plant enclosure.
Client: LJJ Ltd
Date: January 2023
Location:
British Museum Archaeological Research Centre, Reading
Overview:
Using our all terrain telehandler, our movement specialists installed 10no AHUs. Each unit consisted of 5no sections which were double stacked and bolted together once positioned correctly. Our team were also responsible for fitting a number of pumps and vessels within an external plant room.
Client: T Clark
Date: January 2023
Location: Oxford
Overview:
Mechanical Movements were appointed to complete the movement and installation of several small AHUs within the Mercedes Benz showroom in Oxford.
Client: Retail/Leisure Client
Date: January 2023
Location: Stratford, London
Overview:
Mechanical Movements were required to install a variety of plant around the venue, including 2no 6000kg chillers, 3no AHUs, pumps, extract fans and control panels. Anti-vibration mounts and pads were used to prevent disruptive vibrations travelling down into the theatre.
Client: IAC Innovation
Date: November 2022
Location: White Hall Place, Westminster
Overview:
Our operatives fabricated and installed 3no large steel frames to situate all plant onto before lifting a wide variety of plant including, 2no chillers, 2no dry air coolers, 7no AHUs, 6no condensers, 24 pallets of slab, 50no sections of duct work and 100no pieces of pipework. All equipment was lifted using an AT6 mobile tower crane and road closures were implemented throughout works.
Client: BAC
Date: November 2022
Location: Google UK Headquarters, Kings Cross
Overview:
Use of our sturdy artic lorry, 2 x 22tonne rigged lorries and a smaller 7.5tonne lorry to deliver 6 x 15tonne water cooling towers to Google Headquarters. Prior to transportation, each tower was dismantled into 5 manageable sections, facilitating the transportation process.
Client: Commercial Landlord
Date: November 2022
Location: Thames Valley Park, Reading
Overview:
Installing 2no AHUs into a brand-new basement gym. Pallet trucks were used to carefully move the equipment into a small plant room located on the gym floor.
Client: Ocado Group
Date: October 2022
Location: Hatfield, Hertfordshire
Overview:
Removing and replacing cooling systems within the Ocado offices using a LTM1060 crane. We carefully removed 8no 350kg dry air-cooling condensers from the roof plant room, replacing these with 2 newer units. 6no downflow units, each weighing 450kg were also replaced within the live server rooms.
Client: Commercial Consultant
Date: October 2022
Location: White City, West London
Overview:
Use of a 22-ton rigged Hiab lorry to replace a 1500kg plate heat exchanger within a basement plant room.
Client: Make One
Date: October 2022
Location: Camden, London
Overview:
Use of a 22-ton rigged Hiab lorry to lift a 600kg door, fitting it back onto the side of the KOKO building, a renowned music venue in Camden.
Client: Parkeray
Date: October 2022
Location: Clerkenwell, London
Overview:
Utilising a mobile Bocker crane to lift 2no condensers, 14m high onto the roof level of the commercial property. Each 370kg condenser was carefully lifted at an 18m radius, before being placed onto Big Foot support systems.
Client: Innovation Air Conditioning and Building Services
Date: October 2022
Location: Islington, London
Overview:
Using an AT6 mobile tower crane to lift 1no AHU into the rear lower ground plant room. The AHU was split into 3 manageable sections, with the heaviest section weighing 2170kg. Following the completion of the ground-level works, 4no condensers were lifted into the roof plant room and manoeuvred into their final positions.
Client: Working Environments
Date: September 2022
Location: Woking, Surrey
Overview:
Following the careful storage and delivery of the plant, a Hiab lorry was used to lift all units onto site. The new plant included 1no 3.5 tonne heat pump, 2no 900kg buffer vessels, 3no 500-800kg plate heat exchangers and 2no side stream filters, and a telehandler was utilised to shift all equipment into its final position.
Client: Ergro
Date: September 2022
Location: Holborn, London
Overview:
Using a Terex Challenger 3180, we completed a chiller replacement job, removing 2no chillers from the roof of the property. Once all redundant plant had been removed, we were required to lift 4no condensers and 2no MVHRs into the building, carefully manoeuvring them into their final positions.
Client: Designer Group
Date: August 2022
Location: Nine Elms, London
Overview:
Storing, delivering and installing 4no cooling towers, 2no control panels and 2no pressurisation units to a new 56-storey mixed-use tower development.
Client: Ergro
Date: August 2022
Location: Clerkenwell, London
Overview:
Completion of a lifting project using a AT7 Spierings crane to remove a substantial 13tonne AHU, replacing it with a newer, more efficient unit.
Client: Easy Cool Solutions
Date: July 2022
Location: Oxford Square, Newbury
Overview:
Completion of a lifting project using a Spierings AT6 crane to successfully lift a 215kg condenser up onto the roof of an office development.
Client: Local Authority
Date: July 2022
Location: Acton, London
Overview:
Installation of 4 plate heat exchangers and 3 new boilers at the new Ark Acton Academy site.
Client: Great Ormond Street Hospital
Date: July 2022
Location: Central London
Overview:
Use of a 46-ton Challenger 3180 crane to complete a chiller replacement project. A stair climber was then used to remove a 600kg plate heat exchanger from a basement plant room.
Client: Commercial Consultant
Date: June 2022
Location: Maidenhead, Berkshire
Overview:
Use of a Demag AC-160 at a 22m radius to successfully lift each 4750kg chiller component into its final position.
Client: Retail/Leisure Client
Date: June 2022
Location: Stratford, London
Overview:
Using a Terex 2500 Telehandler, the Mechanical Movements team safely unloaded a plant skid off of a lorry before operating a hoist to manoeuvre each component up into the mezzanine plant room.
Client: Commercial Consultant
Date: June 2022
Location: The Discovery Centre, Cambridge
Overview:
Complex lifting project using a tower crane to lift 1 x condenser and 3 x carrier chillers into the building, before manoeuvring each unit into its final position within the plant room.
Client: The University of the Arts London
Date: May 2022
Location: Camberwell, London
Overview:
Completion of a boiler changeover. Using a rigged Hiab lorry we removed 2 redundant boilers and associated components, before delivering and installing 2 new boilers.
Client: Box & Charnock
Date: May 2022
Location: Abbey Wood, London
Overview:
Complex lifting project using a Terex Demag AC35 crane to lift 1no generator and 1no CHP into a plant enclosure.
Client: Retail/Leisure Client
Date: May 2022
Location: Buckinghamshire
Overview:
We were required to excavate trenches using a 2.5 tonne machine before installing new heating services and systems throughout the 300-acre estate.
Client: Commercial Consultant
Date: April 2022
Location: Moorgate, London
Overview:
Use of a 100ton crane to complete a contract lift. We were responsible for the storage, delivery and full installation of some substantial commercial HVAC plant.
Client: Ergro
Date: March 2022
Location: Camden, London
Overview:
Plant removal project using a Spierings AT-4 crane at a 44m radius. Redundant equipment was removed from multiple plant areas, including 2no chillers, 3no air handling units, 6no condensers and 2no extract fans.
Client: Commercial Office Client
Date: December 2021
Location: Canary Wharf, London
Overview:
Installing new downflow cooling systems into the European Bank for Reconstruction & Development (EBRD) building.
Client: Commercial Consultant
Date: November 2021
Location: Kings Cross, London
Overview:
Complex lifting project using a crane lift to transport large structural steelwork, along with 2 Dry Air Coolers up onto the roof of a 11 storey tower.
Client: Alcatel Submarine Networks
Date: November 2021
Location: Greenwich
Overview:
Use of a 100ton mobile crane to lift replacement machinery onto a newly fabricated mezzanine level, following a strip out of a redundant mechanical plant.
Client: Retail/Leisure Client
Date: October 2021
Location: Camden, London
Overview:
Use of a 26tonne Bocker truck-mounted crane to lift 3no. panes of glass from a lorry bed at ground level, to the roof of the KOKO building.
Client: Commercial Landlord
Date: October 2021
Location: London
Overview:
Using a 300tonne crane with a 60m luffing jib, the Mechanical Movements team safely managed the placement of chillers and Air Handling Units onto the roof of an office building in New Gate Street.
Client: Commercial Consultant
Date: September 2021
Location: Candleford, Northamptonshire
Overview:
Replacement of ventilation equipment in an underground carpark using a Telehandler 2506 fitted with a scrubber to remove damaged ventilation fans. These were replaced with new 2no. fans which were lifted using block and tackle.
Client: Public Authority
Date: September 2021
Location: Crawley
Overview:
Coordinating the placement of equipment for the heating and ventilation systems of new civic offices in Crawley. This consisted of multiple lifts of new equipment using an onsite tower crane.
Client: Private Client
Date: September 2021
Location: Gravesend, Kent
Overview:
Manoeuvre of a 20ft sailing yacht within the canal basin in Gravesend, using a 55tonne Liebherr mobile crane.
Client: Commercial Consultant
Date: June 2021
Location: London
Overview:
Use of specialist lifting equipment to complete a coil replacement in the water tower of an iconic bank building.
Client: AkzoNobel
Date: June 2021
Location: Slough, Berkshire
Overview:
Lifting project using a 60 tonne mobile crane to lift and manoeuvre 4no. Air Handling Units into a steel frame.
Client: Commercial Landlord
Date: May 2021
Location: Islington, London
Overview:
Contract lift of a new generator onto the roof of a 34m high commercial building, using a Spierings AT6 mobile tower crane.
Client:
Date: May 2021
Location: Norwich
Overview:
Replacement of cooling towers on the roof of Norwich Crown Court, using a 100tonne mobile crane.
Client: Commercial Developer
Date: February 2021
Location: Shorditch
Overview:
Various contract lifts to position commercial heating and air conditioning equipment into the basement of a 12 storey, mixed-use, new build construction site.
Client: Commercial Landlord
Date: January 2021
Location: Westminster
Overview:
Use of on-site tower cranes to lift 3 Air Conditioning units onto the rooftop of a 15storey mixed-use retail and residential building.
Client: Prominent London University
Date: October 2020
Location: Vauxhall, London
Overview:
Storage and delivery of 4 no pump vessel and boiler skids to a Student Accommodation block. Following this, an on-site tower crane was used to hoist the boiler skid packages up to a counter lever deck.
Client: St Peter’s Hospital
Date: October 2020
Location: Chertsey
Overview:
Use of a LT1045 mobile crane to lift two Trane chillers onto the roof of a two-storey hospital building.
Client: Commercial Office Client
Date: July 2020
Location: Tower Hamlets, London
Overview:
Use of a 300ton crane to lift a 6ton generator onto the 10th floor of a 10-storey office building. The unit was then assembled before being manoeuvred into its final position within the plant room.
Client: Royal College of Surgeons
Date: June 2020
Location: Lincoln’s Inn, Central London
Overview:
Use of an on-site tower crane to lift 4 sections of package plantroom onto the roof of a 6-storey learning facility.
Client: Prominent London University
Date: April 2020
Location: White City, London
Overview:
Movement of 8 giant potted trees using flatbed Hiab lorries. This was necessary to make room for the erection of a scaffold hoist which was required for a nearby construction project.
Client: Pheonix
Date: April 2020
Location: Dagenham
Overview:
Lifting project in Dagenham featuring 10 cooling tower vessels which needed bolting into their steel frames.