• Data Centre, Slough

    Date: Nov 2024

    Location:

    Slough

    Overview:

    Removal of two 16-tonne chillers and replacement with two new 13-tonne chillers

  • Great Windmill St, London

    Date: Oct 2024

    Location:

    London

    Overview:

    The removal of 14 aging condensers and the installation of 14 new units, each weighing approximately 300kg.

  • Skanska, Victoria Street

    Date: Sep 2024

    Location:

    London

    Overview:

    An installation of several large mechanical components, including 4-tonne buffer vessels, 3-tonne pump skids, and expansive air handling units (AHUs), in the lower basement of a building within the new redevelopment project on the southern end of Victoria Street.

  • Dolphin House, Grosvenor Road

    Date: Sep 2024

    Location:

    London

    Overview:

    The relocation of a transformer at Dolphin House.

  • The Capital Hotel, London

    Date: Sep 2024

    Location:

    Knightsbridge

    Overview:

    The installation of three new high-efficiency condensers.

  • Student Accommodation, London

    Date: Sep 2024

    Location:

    Billingsgate, Canary Wharf

    Overview:

    An installation of 6-tonne transformers, 5-tonne generators, 8-tonne plate heat exchangers, 3-tonne booster pump sets, 4-tonne sprinkler pump sets, and several control panels.

  • Temple Circus House, Bristol

    Date: Aug 2024

    Location:

     Bristol

    Overview:

    The removal of old Air Handling Units (AHUs) and chillers, in preparation for a new installation.

  • Bank Street, London

    Date: Aug 2024

    Location:

    Canary Wharf

    Overview:

    The removal of 2x 16-tonne chillers and an installation of 2x 25-tonne chillers.

  • Guinness Microbrewery, London

    Date: July 2024

    Location:

    Langley Street, Covent Garden

    Overview:

    Lift and installation of 2 air source heat pumps (ASHP), 1 chiller, 2 buffer vessels, and a booster set.

  • Charing Cross Rd, London

    Date: June 2024

    Location:

    Charing Cross Road, London

    Overview:

    Lift and installation of 1x Generator, 1x Package Plant Room, 4 x Air Handling Units (AHU), 2 x Electrical Panels, and 5 x Condensers.

  • Charing Cross Rd, London

    Date: May 2024

    Location:

    Charing Cross Raod, London

    Overview:

     Installation of 30 condensers and air source heat pumps (ASHP) on the plant deck mezzanine on the roof of the building.

  • Mandrake Spa & Hotel, London

    Date: May 2024

    Location:

    West London

    Overview:

    Crane lift of plant air conditioning units, air handling units (AHUs), pump sets, and packaged plant rooms onto 2 separate plant areas across 2 different roofs of the building.

     

  • Central London

    Date: Apr 2024

    Location:

    Central London

    Overview:

    Removal of 4 redundant chillers, steel work and adjacent pipework. Installation of 2 new 6-tonne chillers along with new steelwork and pipework.

     

  • Oakley Grove School, Coventry

    Date: Apr 2024

    Location:

    Leamington Spa, Coventry

    Overview:

    Installation of 3x Air Source Heat Pumps, 1x Sitewide Heating Pump,1x Electric Transformer, Sundry Pipework, 3x pallets of solar panel equipment, and 4x control panels.

  • Phoenix, Peterborough

    Date: Apr 2024

    Location:

    Peterborough

    Overview:

    50 x 1500kg Internal AHUs, 25 x 4500kg External AHUs, and Internal Switch Gear 2000kg installation.

  • Barnet County Court, Finchley

    Date: Mar 2024

    Location:

    Finchley, Barnet

    Overview:

     2x Mitsubishi Air Source Heat Pumps (ASHP), switch gear and a 1.3 tonne chiller installation.

  • Ergro Group, London

    Date: Feb 2024

    Location:

    Thomas More Square, London

    Overview:

    Delivery and installation of 2x 9.5 tonne chillers.

  • Phoenix, London

    Date: Feb 2024

    Location:

    Coleman St, London

    Overview:

    Delivery and installation of 2x 5-tonne transformers.

  • Dalkia, London

    Date: Jan 2024

    Location:

    Stratford & Islington, London

    Overview:

     Storage, Delivery and installation of loading bay extraction systems at Queen Elizabeth Olympic Park and Sadler’s Wells Theatre.

  • Powis Place, London

    Date: Jan 2024

    Location:

    Bloomsbury, London

    Overview:

    Removal of 2 redundant chillers from the roof, and the replacement of 3 brand new 2.2 tonne chillers using a mobile tower crane.

  • Phoenix, Peterborough

    Date: Jan 2024

    Location:

    Peterborough

    Overview:

     Installation and lift of several external Air Handling Units (AHUs), Internal AHUs and large amounts of switch gear and control panels.

  • Nutwood House, Canterbury

    Date: Oct 2023

    Location:

    Canterbury

    Overview:

    Delivery and Installation of 2x 1.6-tonne chillers using our HIAB lorry positioning the units onto Anti-vibration Mounts (AVM).

  • Dolphin House, London

    Date: Oct 2023

    Location:

    Pimlico, London

    Overview:

    Installation and lowering of a 5-tonne transformer onto a platform in a basement switch room, accessed via a space-restricted lightwell.

  • He Simm Group, Wembley

     

    Client: HE Simm Group

    Date: Sept 2023

    Location:

    Wembley, London

    Overview:

    Transport and installation of several riser pipes and service modules, across 6 x buildings varying in size from 9 to 20 floors

  • Bupa Hospital, Luton

     

    Date: Sept 2023

    Location:

    Luton, London

    Overview:

    Movement and installation of critical plant components, including 2 x 40ft chillers each weighing 9 tonnes, as well as 2 x AHUs each weighing 7 tonnes

  • Power Base, Harley street

     

    Client: Power Base

    Date: August 2023

    Location:

    Harley Street, London

    Overview:

    Transport and installation of a compact 2-tonne chiller and a 950kg ASHP using a Terex Demag AC35L 35-tonne crane.

  • Brighton Hospital, Sussex

    Date: August 2023

    Location:

    Brighton, Sussex

    Overview:

    Using a colossal 300-tonne crane, Mechanical Movements Completed the first of a three-phase operation to replace all chillers at Brighton Hospital, Sussex.

  • Optimise, Canary Wharf

    Client: Optimise Group

    Date: July 2023

    Location:

    Canary Wharf, London

    Overview:

    Removal of all critical building services plant from the roof level of the 23 storey tower at One Cabot Square.

  • Wates Group, Bristol

    Client: Wates Group

    Date: July 2023

    Location:

    Avon Street, Bristol

    Overview:

    Transport and installation of 8 electrical switchgear panels, to a new 5 storey commercial office building for Contractor Wates Group.

  • Ergro Group, Kensington

    Client: Ergro Group

    Date: June 2023

    Location:

    Kensington, London

    Overview:

    Storing and transportation of four new condenser units, using a mobile tower crane and load spreading mats to remove the 28 redundant condensers and place the new ones. Once installed, all condenser debris and equipment were cleared from the site.

  • Maidstone Hospital, Kent

    Date: June 2023

    Location:

    Maidstone, Kent

    Overview:

    Movement and installation of an Air Handling Unit (AHU), using our HIAB lorry to deliver the unit in 7 sections, with the heaviest weighing in at 2300 kg.

  • Boiler Change, Stevenage

    Date: May 2023

    Location:

     Stevenage, Hertfordshire

    Overview:

    Removed the 15-tonne existing boiler from the site before preparing the plant area with load-bearing road plates, pull points, turfers, and hoists, ready for the new and more efficient 12-tonne boiler to be manoeuvred in.

  • Buntingford School,  East Hertfordshire

    Client: Buntingford School

    Date: March 2023

    Location:

     East Hertfordshire

    Overview:

    Installation of Air Handling Units (AHUs) with contactor Morgan Sindall, using our lifting equipment to manoeuvre them into the first floor, and dismantling them alongside the manufacturer’s guidance.

  • Discovery Park, Sandwich

    Client: Discovery Park Commercial Estate

    Date: March 2023

    Location:

    Sandwich, Kent

    Overview:

    Mechanical Movements positioned and assembled four Air Handling Units (AHUs), which were flat-packed and divided into 1500kg sections, using an external goods hoist and gantry to gain access to the roof plant room.

  • White Hart Street, High Wycombe

    Date: March 2023

    Location:

    White Hart Street, High Wycombe

    Overview:

    Lift and install of 2 condensers and flatpack Flackwood Air handling Units delivered using our 26-tonne rigged HIAB lorry.

     

  • Beaumont Hotel, Mayfair

    Client: Vulcan

    Date: February 2023

    Location:

    Mayfair, London

    Overview:

    Lowering of Air Handling Units (AHUs), water heaters, cylinders, pump sets, booster sets and water treatment systems, through a large access opening, into lower basement.

  • Saffron House, Holborn

    Client: Sale

    Date: February 2023

    Location:

    Saffron House, Hatton Garden, Holborn

    Overview:

    Removal of redundant chillers and steel work from the roof level plant room, before using a mobile 100ton crane to lift and install 5no 2500kg chillers, and 2no condensers into the plant enclosure.

  • British Museum Archaeological Research Centre

    Client: LJJ Ltd

    Date: January 2023

    Location:

    British Museum Archaeological Research Centre, Reading

    Overview:

    Using our all terrain telehandler, our movement specialists installed 10no AHUs. Each unit consisted of 5no sections which were double stacked and bolted together once positioned correctly. Our team were also responsible for fitting a number of pumps and vessels within an external plant room.

  • Mercedes Benz Oxford

    Client: T Clark

    Date: January 2023

    Location: Oxford

    Overview:

    Mechanical Movements were appointed to complete the movement and installation of several small AHUs within the Mercedes Benz showroom in Oxford.

  • Sadler’s Wells East Theatre

    Client: Retail/Leisure Client

    Date: January 2023

    Location: Stratford, London

    Overview:

    Mechanical Movements were required to install a variety of plant around the venue, including 2no 6000kg chillers, 3no AHUs, pumps, extract fans and control panels. Anti-vibration mounts and pads were used to prevent disruptive vibrations travelling down into the theatre.

  • White Hall Place

    Client: IAC Innovation

    Date: November 2022

    Location:  White Hall Place, Westminster

    Overview:

    Our operatives fabricated and installed 3no large steel frames to situate all plant onto before lifting a wide variety of plant including, 2no chillers, 2no dry air coolers, 7no AHUs, 6no condensers, 24 pallets of slab, 50no sections of duct work and 100no pieces of pipework. All equipment was lifted using an AT6 mobile tower crane and road closures were implemented throughout works.

  • Google UK Headquarters

    Client: BAC

    Date: November 2022

    Location:  Google UK Headquarters, Kings Cross

    Overview:

    Use of our sturdy artic lorry, 2 x 22tonne rigged lorries and a smaller 7.5tonne lorry to deliver 6 x 15tonne water cooling towers to Google Headquarters. Prior to transportation, each tower was dismantled into 5 manageable sections, facilitating the transportation process.

  • ‘Here’ Building

    Client: Commercial Landlord

    Date: November 2022

    Location:  Thames Valley Park, Reading

    Overview:

    Installing 2no AHUs into a brand-new basement gym. Pallet trucks were used to carefully move the equipment into a small plant room located on the gym floor.

  • Ocado Offices

    Client: Ocado Group

    Date: October 2022

    Location:  Hatfield, Hertfordshire

    Overview:

    Removing and replacing cooling systems within the Ocado offices using a LTM1060 crane. We carefully removed 8no 350kg dry air-cooling condensers from the roof plant room, replacing these with 2 newer units. 6no downflow units, each weighing 450kg were also replaced within the live server rooms.

  • BBC Television Centre

    Client: Commercial Consultant

    Date: October 2022

    Location:  White City, West London

    Overview:

    Use of a 22-ton rigged Hiab lorry to replace a 1500kg plate heat exchanger within a basement plant room.

  • KOKO Camden

    Client: Make One

    Date: October 2022

    Location:  Camden, London

    Overview:

    Use of a 22-ton rigged Hiab lorry to lift a 600kg door, fitting it back onto the side of the KOKO building, a renowned music venue in Camden.

  • 17 Clerkenwell Close

    Client: Parkeray

    Date: October 2022

    Location:  Clerkenwell, London

    Overview:

    Utilising a mobile Bocker crane to lift 2no condensers, 14m high onto the roof level of the commercial property. Each 370kg condenser was carefully lifted at an 18m radius, before being placed onto Big Foot support systems.

  • Porters House

    Client: Innovation Air Conditioning and Building Services

    Date: October 2022

    Location:  Islington, London

    Overview:

    Using an AT6 mobile tower crane to lift 1no AHU into the rear lower ground plant room. The AHU was split into 3 manageable sections, with the heaviest section weighing 2170kg. Following the completion of the ground-level works, 4no condensers were lifted into the roof plant room and manoeuvred into their final positions.

  • Midas House

    Client: Working Environments

    Date: September 2022

    Location: Woking, Surrey

    Overview:

    Following the careful storage and delivery of the plant, a Hiab lorry was used to lift all units onto site. The new plant included 1no 3.5 tonne heat pump, 2no 900kg buffer vessels, 3no 500-800kg plate heat exchangers and 2no side stream filters, and a telehandler was utilised to shift all equipment into its final position.

  • Swan House

    Client: Ergro

    Date: September 2022

    Location: Holborn, London

    Overview:

    Using a Terex Challenger 3180, we completed a chiller replacement job, removing 2no chillers from the roof of the property. Once all redundant plant had been removed, we were required to lift 4no condensers and 2no MVHRs into the building, carefully manoeuvring them into their final positions.

  • One Nine Elms

    Client: Designer Group

    Date: August 2022

    Location: Nine Elms, London

    Overview:

    Storing, delivering and installing 4no cooling towers, 2no control panels and 2no pressurisation units to a new 56-storey mixed-use tower development.

  • City University London

    Client: Ergro

    Date: August 2022

    Location: Clerkenwell, London

    Overview:

    Completion of a lifting project using a AT7 Spierings crane to remove a substantial 13tonne AHU, replacing it with a newer, more efficient unit.

  • St Anthony’s House

    Client: Easy Cool Solutions

    Date: July 2022

    Location: Oxford Square, Newbury

    Overview:

    Completion of a lifting project using a Spierings AT6 crane to successfully lift a 215kg condenser up onto the roof of an office development.

  • Ark Acton Academy

    Client: Local Authority

    Date: July 2022

    Location: Acton, London

    Overview:

    Installation of 4 plate heat exchangers and 3 new boilers at the new Ark Acton Academy site.

  • Great Ormond Street Hospital

    Client: Great Ormond Street Hospital

    Date: July 2022

    Location: Central London

    Overview:

    Use of a 46-ton Challenger 3180 crane to complete a chiller replacement project. A stair climber was then used to remove a 600kg plate heat exchanger from a basement plant room.

  • AbbVie House

    Client: Commercial Consultant

    Date: June 2022

    Location: Maidenhead, Berkshire

    Overview:

    Use of a Demag AC-160 at a 22m radius to successfully lift each 4750kg chiller component into its final position.

  • Sadler’s Wells East Building

    Client: Retail/Leisure Client

    Date: June 2022

    Location: Stratford, London

    Overview:

    Using a Terex 2500 Telehandler, the Mechanical Movements team safely unloaded a plant skid off of a lorry before operating a hoist to manoeuvre each component up into the mezzanine plant room.

  • Astrazeneca Campus

    Client: Commercial Consultant

    Date: June 2022

    Location: The Discovery Centre, Cambridge

    Overview:

    Complex lifting project using a tower crane to lift 1 x condenser and 3 x carrier chillers into the building, before manoeuvring each unit into its final position within the plant room.

  • Brooke Hall Student Accommodation

    Client: The University of the Arts London

    Date: May 2022

    Location: Camberwell, London

    Overview:

    Completion of a boiler changeover. Using a rigged Hiab lorry we removed 2 redundant boilers and associated components, before delivering and installing 2 new boilers.

  • Abbey Place

    Client: Box & Charnock

    Date: May 2022

    Location: Abbey Wood, London

    Overview:

    Complex lifting project using a Terex Demag AC35 crane to lift 1no generator and 1no CHP into a plant enclosure.

  • Stoke Park Golf Club & Hotel

    Client: Retail/Leisure Client

    Date: May 2022

    Location: Buckinghamshire

    Overview:

    We were required to excavate trenches using a 2.5 tonne machine before installing new heating services and systems throughout the 300-acre estate.

  • Habib Bank

    Client: Commercial Consultant

    Date: April 2022

    Location: Moorgate, London

    Overview:

    Use of a 100ton crane to complete a contract lift. We were responsible for the storage, delivery and full installation of some substantial commercial HVAC plant.

  • Swiss Cottage Library

    Client: Ergro

    Date: March 2022

    Location: Camden, London

    Overview:

    Plant removal project using a Spierings AT-4 crane at a 44m radius. Redundant equipment was removed from multiple plant areas, including 2no chillers, 3no air handling units, 6no condensers and 2no extract fans.

  • Bank Street

    Client: Commercial Office Client

    Date: December 2021

    Location: Canary Wharf, London

    Overview:

    Installing new downflow cooling systems into the European Bank for Reconstruction & Development (EBRD) building.

  • 4 Handyside Street

    Client: Commercial Consultant

    Date: November 2021

    Location: Kings Cross, London

    Overview:

    Complex lifting project using a crane lift to transport large structural steelwork, along with 2 Dry Air Coolers up onto the roof of a 11 storey tower.

  • Greenwich Mechanical Plant

    Client: Alcatel Submarine Networks

    Date: November 2021

    Location: Greenwich

    Overview:

    Use of a 100ton mobile crane to lift replacement machinery onto a newly fabricated mezzanine level, following a strip out of a redundant mechanical plant.

  • KOKO Camden

    Client: Retail/Leisure Client

    Date: October 2021

    Location: Camden, London

    Overview:

    Use of a 26tonne Bocker truck-mounted crane to lift 3no. panes of glass from a lorry bed at ground level, to the roof of the KOKO building.

  • New Gate Street

    Client: Commercial Landlord

    Date: October 2021

    Location: London

    Overview:

    Using a 300tonne crane with a 60m luffing jib, the Mechanical Movements team safely managed the placement of chillers and Air Handling Units onto the roof of an office building in New Gate Street.

  • Underground Carpark Candleford

    Client: Commercial Consultant

    Date: September 2021

    Location: Candleford, Northamptonshire

    Overview:

    Replacement of ventilation equipment in an underground carpark using a Telehandler 2506 fitted with a scrubber to remove damaged ventilation fans.  These were replaced with new 2no. fans which were lifted using block and tackle.

  • Crawley Civic Offices

    Client: Public Authority

    Date: September 2021

    Location: Crawley

    Overview:

    Coordinating the placement of equipment for the heating and ventilation systems of new civic offices in Crawley.  This consisted of multiple lifts of new equipment using an onsite tower crane.

  • Gravesend Canal Basin

    Client: Private Client

    Date: September 2021

    Location: Gravesend, Kent

    Overview:

    Manoeuvre of a 20ft sailing yacht within the canal basin in Gravesend, using a 55tonne Liebherr mobile crane.

  • Canary Wharf

    Client: Commercial Consultant

    Date: June 2021

    Location: London

    Overview:

    Use of specialist lifting equipment to complete a coil replacement in the water tower of an iconic bank building.

  • AkzoNobel Offices

    Client: AkzoNobel

    Date: June 2021

    Location: Slough, Berkshire

    Overview:

    Lifting project using a 60 tonne mobile crane to lift and manoeuvre 4no. Air Handling Units into a steel frame.

  • Vale Royal

    Client: Commercial Landlord

    Date: May 2021

    Location: Islington, London

    Overview:

    Contract lift of a new generator onto the roof of a 34m high commercial building, using a Spierings AT6 mobile tower crane.

  • Norwich Crown Court

    Client:

    Date: May 2021

    Location: Norwich

    Overview:

    Replacement of cooling towers on the roof of Norwich Crown Court, using a 100tonne mobile crane.

  • Featherstone Street

    Client: Commercial Developer

    Date: February 2021

    Location: Shorditch

    Overview:

    Various contract lifts to position commercial heating and air conditioning equipment into the basement of a 12 storey, mixed-use, new build construction site.

  • Westminster Air Conditioning

    Client: Commercial Landlord

    Date: January 2021

    Location: Westminster

    Overview:

    Use of on-site tower cranes to lift 3 Air Conditioning units onto the rooftop of a 15storey mixed-use retail and residential building.

  • Student Accommodation Block, London

    Client: Prominent London University

    Date: October 2020

    Location: Vauxhall, London

    Overview:

    Storage and delivery of 4 no pump vessel and boiler skids to a Student Accommodation block.  Following this, an on-site tower crane was used to hoist the boiler skid packages up to a counter lever deck.

  • St Peter’s Hospital

    Client: St Peter’s Hospital

    Date: October 2020

    Location: Chertsey

    Overview:

    Use of a LT1045 mobile crane to lift two Trane chillers onto the roof of a two-storey hospital building.

  • Commercial Office Tower Hamlets

    Client: Commercial Office Client

    Date: July 2020

    Location: Tower Hamlets, London

    Overview:

    Use of a 300ton crane to lift a 6ton generator onto the 10th floor of a 10-storey office building.  The unit was then assembled before being manoeuvred into its final position within the plant room.

  • Lincoln’s Inn Lift

    Client: Royal College of Surgeons

    Date: June 2020

    Location: Lincoln’s Inn, Central London

    Overview:

    Use of an on-site tower crane to lift 4 sections of package plantroom onto the roof of a 6-storey learning facility.

  • White City

    Client: Prominent London University

    Date: April 2020

    Location: White City, London

    Overview:

    Movement of 8 giant potted trees using flatbed Hiab lorries. This was necessary to make room for the erection of a scaffold hoist which was required for a nearby construction project.

  • Dagenham Data Centre

    Client: Pheonix

    Date: April 2020

    Location: Dagenham

    Overview:

    Lifting project in Dagenham featuring 10 cooling tower vessels which needed bolting into their steel frames.