Looking back to 2019, here we were on-site at Reading University, supporting the development of a new teaching facility on campus.

Working for Briggs & Forrester, over a 12-day programme, we used a 60-tonne crane to position all the new mechanical plant equipment into place, via an access roof hatch on the new 27m high structure.

The HVAC plant we were responsible for positioning included commercial chillers, boilers, AHUs (air handling units) and the associated plant, all of which was lifted successfully without a hitch, facilitating the continued successful delivery of the overall M&E installation by the contractors.