Another Successful Chiller Installation by Mechanical Movements 🏢

Last weekend, our dedicated team successfully completed a complex chiller replacement project.

This work involved the removal of a redundant 7-tonne chiller, acoustic enclosure, and other various components. In their place, we installed a new 9-tonne chiller along with an acoustic enclosure and the necessary components.

The project was carried out using a Tando AC7.450 mobile crane, rigged with 100 tonnes of ballast weight and a 27m luffing jib, capable of achieving an impressive 14.9 tonnes at a 38m working radius. 🏗️

Additionally, another team worked in the building’s plant areas to complete a pump changeover, utilizing A-frames and bespoke lifting equipment.

The project ran smoothly from 7am Sunday until 1am Monday—a true testament to the team’s expertise and dedication!