Chiller Change Over at Thomas More Square…
Last weekend Mechanical Movements were appointed by one of our longstanding clients Ergro Group to complete a chiller changeover at Thomas More Square, London.
The works consisted of the storage, delivery and installation of 2x 9.5-tonne chillers, as well as the removal of the 2 redundant chillers using a 120-tonne crane to complete the changeover.
To handle the weight and integrity of the new chillers, a bespoke lifting frame was required for a 10-point direct lift. Mechanical Movements also took responsibility for traffic management, road closure, and diversions in the area, which is typically quite busy.
Our lifting experts did a great job ensuring all was lifted and installed correctly following all necessary health and safety precautions.