Delivery & Installation in the Heart of London…

Last week, Phoenix assigned Mechanical Movements to deliver and install two 5-tonne transformers on Coleman St, in the City of London.

Before arriving at the site, the team dismantled the transformers to help manoeuvre them through the tight corridors within the building. Using a steel beam that had been previously load-tested in the Woolgate Exchange basement loading area, both units were lowered into the basement.

Once in the basement, the team carefully and strategically handled each transformer along and around the lower basement corridors before placing them in their final positions in the high-voltage plant rooms.

Well done to the specialist installation team for successfully completing this challenging installation while ensuring that all components were installed safely following the manufacturer’s guidelines.