Chiller Replacement in Canary Wharf…

Over the past month, the Mechanical Movements team has been working alongside Metropolitan on the chiller replacement project at Morgan Stanley Bank Street offices.

The project encompassed the removal of a redundant 16-tonne chiller to make room for the seamless installation of a new 25-tonne chiller. Our adept team utilised a diverse range of specialised moving and lifting equipment, including articulated lorries, heavy lift hi-abs, telehandlers, custom wheeled stillages, and numerous heavy lift porta gantries to effortlessly complete the installation of these substantial and weighty components.

The team executed their tasks flawlessly in a confined space, ensuring safety and precision. They completed 2 chiller installations in a matter of days, removing 2 redundant chillers and replacing them with 2 new ones. They are now ready to tackle the remaining 4 installations with the same level of expertise and efficiency.