“Highest Central London Crane Lift in 1.5 Years”

Our team were extremely proud to recently successfully complete this very prominent and historic lifting operation, for Designer Group in Central London.

The plant installation project took place at One Nine Elms, a new 56-storey mixed-use tower development, accommodating 730,000 sq ft of residential apartments and 1,000 sq ft of retail outlets.

Storing, delivering and installing the 4no cooling towers, 2no control panels and 2no pressurisation units to such a towering height, required our project team to thoroughly prepare this programme ensuring that every minor detail and potential risk was comprehensively prepared for.

We lifted all units into their positions onto roof level using the onsite tower crane, utilising a man rider to de-rig each item and bigfoot systems to secure them into exact locations, along with anti-vibration mounts.

The entire project went as smoothly as planned, with everyone keeping safety at the very forefront of each delivery stage.